Week 1: Demo and rough plumbing
Fixtures, tile and the old tub come out; floors and walls open where the plan requires. Plumbers re-route supplies and drains for the new layout — a shower valve lands where the tub filler used to be — and any subfloor or joist damage gets repaired while it is visible, not covered. Surprises concentrate in this week, which is why we schedule it first and price the common ones in writing.
Weeks 2–3: Waterproofing, tile and the slow-looking middle
The shower gets its waterproofing membrane — the layer that decides whether this bathroom lasts thirty years — followed by tile on floors and walls. Tile is methodical work: layout, setting, curing, grouting. To a homeowner it looks slow; to a tile setter it is the difference between a shower that sheds water and one that absorbs it. Electrical trim for heated floors, fans and lighting happens in the same window, before the county's inspections where your county requires them.
Weeks 4–5: Vanity, fixtures and glass
The vanity and counter go in, faucets and the toilet are set, and the room starts to look like the rendering. Custom glass is templated only after tile is final — glass is measured to the finished opening, never guessed — and its fabrication runs about two weeks, which is why glass is often the last piece even when everything else is done.
Final weeks: Paint, punch list and the walk-through
Paint, mirrors, hardware, accessories and a deep clean close the job, then we walk it with you and list every nick and adjustment before final payment. What actually moves a finish date? Late tile or fixture deliveries, a surprise in the walls, and mid-project scope changes — all three are managed by ordering before demo and keeping decisions ahead of the crew. Planning a bath of your own? Our bathroom remodeling page lays out the process, and a free estimate starts the clock: call (240) 266-8317.
Frequently asked questions
Can I use my bathroom during the remodel?
The bathroom being remodeled is out of service for most of the project. Most homes have a second bath; for single-bath homes we sequence the work to restore a working toilet as early as possible and plan the schedule around you.
Why does shower glass take so long?
Custom glass is templated after tile is complete, then cut, tempered and hardware-matched off-site — about two weeks. Tempering cannot be rushed or re-cut, so measuring the finished opening is non-negotiable.
Do bathroom remodels need permits in Maryland?
When plumbing, electrical or walls move — most full remodels — yes. We file the permits and schedule inspections as part of the project in every county we serve.